Construction of the Social Residence Hall. Stages

By | Social hostel for the orphanage leavers in the cit

Let us sum up the results of one of the most serious stages of the construction of the Social Residence Hall for graduates of orphanages in the city of Aktobe.

Today, at the facility, the work on installing the off-site general utilities has been fully completed, and all relevant documents have been submitted to government agencies so that the facility will be accepted into service.

The interior finishing works in all the residential facilities have also been completed, the finishing work on the site improvement are scheduled for the spring.

A new social facility has been opened in Aktobe

By | Social hostel for the orphanage leavers in the cit

A new social facility has been opened in Aktobe Saby Charitable Fund has opened a new Meyіrіm Center of a Youth Social Adaptation designed for the personal accommodation of orphan asylum graduates and their quicker adaptation for an adult life in Aktobein honor of the 25th anniversary of Independence of the Republic of Kazakhstan.

BerdybekSaparbayev,an akim of Aktobe region, Ilyas Ispanov,an Akim of Aktobe, as well as Kenes Rakishev, a well-known businessman, philanthropist and Saby co-founder, participated in the Centeropening. The most welcome holiday guests became its future residentsthemselves, because they will not only live herebut willalsoget the basics of their future profession.

An administrative building for the organization of ajob training process and leisure-time activities of center pupils wasalready fully accommodated;a sewing workshop, a shoe-repair shop, a flower shop, a beauty salon, an assembly hall and a hall of physical therapy is equipped with the necessary equipment. Also, a two-storied residential building with 16 single-bedroom apartments wasfinished in a fine finish, first floor of which is designed for personal accommodation of wheelchair persons.

A completion of the second phase of the construction, a complete accommodation of residents, a landscaping and site finishing, as well as an installation of sports grounds is scheduled in spring of 2017. We sincerely wish Meyіrіm center to open a new targetfor the children to their independent life with a demanded profession in their holdfast.

Construction of Social Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

Construction of social dormitory for leavers of boarding schools in Aktobe city is in progress.

For the past four months favorable conclusions of complex independent expertise on the main design estimate documentation of the project and external supply lines were received. Corresponding notifications of start-up production of installation and construction works in the local State Architectural and Construction Supervision Authority were registered. Preparatory works of top soil territory clearing were carried out, the land parcel fencing was fixed, temporary communication lines of necessary power were installed. The development of excavations and concrete blinding were fulfilled to 100%.

At present the works of foundation installation of 4 living blocks and one office block are being carried out.

Dormitory Construction. Stages

By | Social hostel for the orphanage leavers in the cit

The regular significant stage of realization of dormitory construction in Aktobe city has been completed.

The Design estimate documentation has been fully developed. At the present time the process of its approval in relevant authorities and preparation of its submission for the state expert appraisal is being performed.

The development of off-site utilities design estimate documentation has been also completed. Necessary agreements have been received; the project has been submitted for the state expertise.

Construction of Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

The development of design and estimate documentation (DED) for the construction of dormitory in Aktobe city is continued.

To the present time, the official act on land parcel has been executed, geodetic and geological examinations have been performed, sketch plan has been accepted, all technical conditions from corresponding authorities and architectural planning assessment have been received.

The works of land parcel cleaning and layout, fencing assemblage, as wells as temporary facilities installation have been started.

Construction of Social Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

To the present time, the works of engineering and geological research on the construction site of Social Dormitory for boarding school leavers have been completed.

16 exploration wells were drilled, in the result of which 26 soil samples were selected for laboratory evaluations of their qualities and composition.

Field documentation of drilled wells and results of laboratory investigations became the basis for drawing of the technical report of engineering and geological research, prepared by one of the contractors.

Construction of Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

The land parcel with total area of 3 ha was allocated for the construction of dormitory for graduates of boarding schools, who have some health problems, by the Akimat of Aktobe city in February of the present year.

We have received all necessary adjustments in reviewing and controlling authorities, land use project has been prepared, as well as topographic-geodesic works have been performed on the land parcel.

At the present time the resolution of Akimat for engineering and construction works of the object is being prepared, after which we will start to process Architectural and Planning Assignment and technical specifications of operating entities.

Building of Societal Residence Hall. Stages

By | Social hostel for the orphanage leavers in the cit

Building of Societal Residence Hall. Stages ‘Saby’ Charitable Foundation goes on implementing the project of building of societal residence hall for the foster homes leavers in Aktobe city. The pilot project has been developed by this moment, and it is passing the confirmation procedure in the correspondent authorities now.

As per the building project at the land parcel 2.7 ha there will be built two section-type 2-storied townhouses with two entrance hallways and two section-type 2-storied townhouses with three entrance hallways, which have general residential capacity – 80 places; the ground floors of these townhouses will be destined for the residence of the wheel-chair persons. At the ground floor of every section there are entrance hall with double-height ante-room, passage-ways and cage, as well as four one-room flats with area 41 sq.m. each. All flats include a hall, a bathroom, a living room, a kitchen and stanzas. At the first floor there are also 4 one-room flats on each section.

Administrative building is intended to provide control and services for this residence hall, as well as to arrange educational process and to provide leisure activities for the fosters residing in this residence hall. For these purposes there are director’s office including reception, accountant office, other offices, utility rooms. Educational and production areas include: hairdressing salon, photo-copying shop, shoes repairing shop and sewing shop, where the fosters, residing here, will study the occupations, have occupational practice and work activities, what will ensure their basic financial sufficiency and, as a result, social rehabilitation. In the public area of the administrative building there are events hall and sports and rehabilitation gym including change rooms. The technical section will be located behind the events hall. At the plot there is also boiler house intended to provide heating.

At the territory of institution there will be provided multifunctional sports ground for the play sports, section of training simulators intended to go in for sport outside, parking on 30 cars, section of technical constructions.

Moreover, the improvement of the land plot is provided as per the project: asphalt travelling ways, pavements, paved garden and walking paths, necessary for convenient connection between buildings and construction, will be placed with meeting all fire safety requirements; as well the flower gardens and grass plots, low architectural forms, green spaces will be provided there.

General area of the land plot is 4,03 ha, useful area 2,70 ha. General building area amounts approximately 4 300 sq.m. All the objects will meet up-to-date requirements of the regulatory documents of the Republic of Kazakhstan.

Photos here.

Building of Residential Community in Aktobe

By | Social hostel for the orphanage leavers in the cit

‘Saby’ Charitable Foundation in scope of the Project ‘Orkendeu’ starts the building of a residential community in Aktobe city for the boarding schools’ graduates who have health disabilities.

This decision has been made on the basis of the data obtained due to the meetings and consultations with the agents of guardianship and wardship authority in Aktobe city as well as after the meeting with Akim of Aktobe city, Aktobe region who were sympathetic to endorse this initiative.

According to available information currently there is only one operating House for youth, which is the institution for the social adaptation of orphan children and for the children without parental care come to this House after graduating the regional boarding schools. This House is 1971 year built, it is obsolete and worn-out; it’s designated for 100 places but it is permanently overcrowded as children from all over the region come here. Besides the vacant places are deficit there is also a real problem for the boarding schools’ graduates with mental disabilities, need independent residence as they need more time for adaptation and permanent social-psychological support. It’s urgent need to build new building to provide the residence to such group of children.

According to socioeconomic project rationale there is proposition to build a range of 2-floor townhouses with total capacity 80 places; the ground floors of these houses will be designated for the wheelchair users’ accommodation. We are as well planning to build mini-shops to provide possibility of the labour adaptation to the educatees and also the possibility to work and become financially sufficient. Moreover building of gym, events hall and sports ground is also provisioned. All the objects will meet requirements of the currently valid regulatory documents of the Republic of Kazakhstan. The total area of buildings and facilities will amount approximately 6 000 sq.m.

‘Saby’ Charitable Foundation undertakes upon designing, building and complete equipping of the residential community as well the landscaping and general improvement of the territory. After all the works will have been completed and the object will be commissioned ‘Turnkey’, so the object is transferred to the ownership of regional akimat for it to provide the further financing and to support its operation.