Construction of Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

The development of design and estimate documentation (DED) for the construction of dormitory in Aktobe city is continued.

To the present time, the official act on land parcel has been executed, geodetic and geological examinations have been performed, sketch plan has been accepted, all technical conditions from corresponding authorities and architectural planning assessment have been received.

The works of land parcel cleaning and layout, fencing assemblage, as wells as temporary facilities installation have been started.

Construction of School for 1200 places in Almaty city

By | The High-school for 1200 places at the Almaty cit

Construction of School for 1200 places in Almaty city “Saby” Charitable Foundation within the framework of “Orkendeu” project has started the construction of one more major project – Secondary school for 1200 places on the fixed land parcel located to the west from Akzhar village of Nauryzbai district of Almaty city.

This project is realized under the concluded agreement with the Akimat of Almaty city, according to which the Foundation undertakes to build a school upon the project provided by the Akimat at its own account, following which the Foundation will donate to the city the school on a free-of-charge basis.

By now, the design and estimate documentation on the state order is fully prepared. Favorable conclusion of the state expert appraisal was received.

According to the working project, the school building will be located on the land parcel of 3,0026 ha in area and will include ten two- and three-storey blocks with basement level, total area of buildings – 11 625 sq.m.

Dressing rooms for junior school, offices for Deputy Principal, rooms for technical staff and accounting office are placed on the 1st block.
Sports hall, security office and events hall for 360 seats are situated on the 2nd block.
Sports hall, public fund of library, closed fund of library and multimedia library are specified on the 3rd block.
On the 4th block, classrooms of junior school will be placed on the first and second floors and classrooms of senior school – on the third floor.
Groups of buildings for junior and senior school, dressing room, classroom of basic military training with arms room, reception room, Principal’s office, teacher’s room and radio center are specified on the 5th block.
Rooms of school-wide purposes are situated on the 6th and 7th blocks.
On the 8th block the following rooms will be located: dressing rooms for girls and boys, wash rooms, preschool classrooms, multimedia rooms, laboratory rooms, classrooms for junior school, tiring-room, groups of classrooms for middle and senior school, computer rooms with laboratory rooms and a room of textile processing for girls of 5-9 forms.
Classrooms of middle and senior school, classroom of chemistry with laboratory and laboratory room, workrooms of metal and wood processing, tool room, classroom of physics with laboratory and laboratory room, classroom of foreign language, classroom of biology with laboratory and laboratory room, as well as medical rooms: examination room, consulting room, room of Speech and Language Pathologist are situated on the 9th block.
Food court with dining hall for 200 seats is provided in the 10th block. Food court includes the following: loading room, room for refrigerators; dry goods area, vegetable storeroom, cold food room, flour room, meat and fish room, vegetable room; hot shops with service counter; washing rooms for tableware and cookware; dining room for 200 seats; staff room with shower room, wet unit; cleaning tools storeroom; feeding of pupils of all age is organized in the dining hall.

Classrooms are designed with left-sided lighting, occupied place is calculated for 25 persons. Demonstration place of a teacher in the classrooms of physics, chemistry and labour training according to the requirements of educational process is leveled up to 20 cm from the floor line. Physics and chemistry classrooms are designed for all kinds of lessons.

Windows, leaded lights, entrance doors are made of reinforced plastic. Energy saving glass cover is used in warning lights constructions. Interior doors are wooden. Interior finishing has been performed according to the sanitary norms. Exterior finishing – plaster with succeeding painting of decorative tile underside. Pedestal base – facade paving-tile. Finishing of porch of main entrance and additional entrances – deck tile.
The systems of fire warning and video control are provided in a mandatory manner.

Functional separation of the school territory is provided by the general layout on the following areas: school area, educational and experimental area, sports area, leisure area and utility area.

For landscaping the school grounds are provided the various types of hard coatings. For driveways and grounds was applied the asphalt-concrete surfacing, on the territory of the site for school-wide events – paving slabs coating, according to the requirements of SNiP. In the rest of the territory for the sidewalks, paths and sites is projected the asphalt-concrete surfacing. For the ease of movement of people with limited mobility the external ramps, and in a parking – car parking spaces for disabled persons, with width 3.50 m, is provided in the project.

On the territory will be located various hardscape elements and portable equipment. On the sites of the school main entrances will be installed decorative benches, rubbish bins and vases with flowers and ornamental plants. The territory of the plot, free of buildings, roads and sites is planting with trees and shrubs, flower beds and laying down as lawn, taking into account the ornamental characteristics of plants and functional purpose of landscaping and resistance to the local climatic conditions. In a mandatory manner is made the ordinary planting of the trees and shrubs along the fence of the school territory.

In the areas for active leisure is set the different equipment for outdoor games for children according to age. In the areas for physical education and sports will be installed the equipment for the implementation of educational programs for physical education, and for conducting of sports and recreational events. On the areas for outdoor activities that designed for ball games, is used special rubber coating, the rest of the area is laying down as lawn. Educational- experimental area is equipped with a canopy for outdoors biology lessons. The benches and rubbish bins are also at sites for outside activities and in the area for physical education and sports.

Throughout the school territory is provided outdoor lighting with automatic switches. On the perimeter is set grating fence with height 1.80 m with the installation of swinging gates and wickets at the entrances and driveways.

The project is realized according to SNiP and sanitary norms of the Republic of Kazakhstan.

Construction of Social Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

To the present time, the works of engineering and geological research on the construction site of Social Dormitory for boarding school leavers have been completed.

16 exploration wells were drilled, in the result of which 26 soil samples were selected for laboratory evaluations of their qualities and composition.

Field documentation of drilled wells and results of laboratory investigations became the basis for drawing of the technical report of engineering and geological research, prepared by one of the contractors.

Construction of Dormitory. Stages

By | Social hostel for the orphanage leavers in the cit

The land parcel with total area of 3 ha was allocated for the construction of dormitory for graduates of boarding schools, who have some health problems, by the Akimat of Aktobe city in February of the present year.

We have received all necessary adjustments in reviewing and controlling authorities, land use project has been prepared, as well as topographic-geodesic works have been performed on the land parcel.

At the present time the resolution of Akimat for engineering and construction works of the object is being prepared, after which we will start to process Architectural and Planning Assignment and technical specifications of operating entities.

Building of Societal Residence Hall. Stages

By | Social hostel for the orphanage leavers in the cit

Building of Societal Residence Hall. Stages ‘Saby’ Charitable Foundation goes on implementing the project of building of societal residence hall for the foster homes leavers in Aktobe city. The pilot project has been developed by this moment, and it is passing the confirmation procedure in the correspondent authorities now.

As per the building project at the land parcel 2.7 ha there will be built two section-type 2-storied townhouses with two entrance hallways and two section-type 2-storied townhouses with three entrance hallways, which have general residential capacity – 80 places; the ground floors of these townhouses will be destined for the residence of the wheel-chair persons. At the ground floor of every section there are entrance hall with double-height ante-room, passage-ways and cage, as well as four one-room flats with area 41 sq.m. each. All flats include a hall, a bathroom, a living room, a kitchen and stanzas. At the first floor there are also 4 one-room flats on each section.

Administrative building is intended to provide control and services for this residence hall, as well as to arrange educational process and to provide leisure activities for the fosters residing in this residence hall. For these purposes there are director’s office including reception, accountant office, other offices, utility rooms. Educational and production areas include: hairdressing salon, photo-copying shop, shoes repairing shop and sewing shop, where the fosters, residing here, will study the occupations, have occupational practice and work activities, what will ensure their basic financial sufficiency and, as a result, social rehabilitation. In the public area of the administrative building there are events hall and sports and rehabilitation gym including change rooms. The technical section will be located behind the events hall. At the plot there is also boiler house intended to provide heating.

At the territory of institution there will be provided multifunctional sports ground for the play sports, section of training simulators intended to go in for sport outside, parking on 30 cars, section of technical constructions.

Moreover, the improvement of the land plot is provided as per the project: asphalt travelling ways, pavements, paved garden and walking paths, necessary for convenient connection between buildings and construction, will be placed with meeting all fire safety requirements; as well the flower gardens and grass plots, low architectural forms, green spaces will be provided there.

General area of the land plot is 4,03 ha, useful area 2,70 ha. General building area amounts approximately 4 300 sq.m. All the objects will meet up-to-date requirements of the regulatory documents of the Republic of Kazakhstan.

Photos here.

Building of Residential Community in Aktobe

By | Social hostel for the orphanage leavers in the cit

‘Saby’ Charitable Foundation in scope of the Project ‘Orkendeu’ starts the building of a residential community in Aktobe city for the boarding schools’ graduates who have health disabilities.

This decision has been made on the basis of the data obtained due to the meetings and consultations with the agents of guardianship and wardship authority in Aktobe city as well as after the meeting with Akim of Aktobe city, Aktobe region who were sympathetic to endorse this initiative.

According to available information currently there is only one operating House for youth, which is the institution for the social adaptation of orphan children and for the children without parental care come to this House after graduating the regional boarding schools. This House is 1971 year built, it is obsolete and worn-out; it’s designated for 100 places but it is permanently overcrowded as children from all over the region come here. Besides the vacant places are deficit there is also a real problem for the boarding schools’ graduates with mental disabilities, need independent residence as they need more time for adaptation and permanent social-psychological support. It’s urgent need to build new building to provide the residence to such group of children.

According to socioeconomic project rationale there is proposition to build a range of 2-floor townhouses with total capacity 80 places; the ground floors of these houses will be designated for the wheelchair users’ accommodation. We are as well planning to build mini-shops to provide possibility of the labour adaptation to the educatees and also the possibility to work and become financially sufficient. Moreover building of gym, events hall and sports ground is also provisioned. All the objects will meet requirements of the currently valid regulatory documents of the Republic of Kazakhstan. The total area of buildings and facilities will amount approximately 6 000 sq.m.

‘Saby’ Charitable Foundation undertakes upon designing, building and complete equipping of the residential community as well the landscaping and general improvement of the territory. After all the works will have been completed and the object will be commissioned ‘Turnkey’, so the object is transferred to the ownership of regional akimat for it to provide the further financing and to support its operation.

Children’s Village is not Built in Astana

By | Children's villages of family type in Astana

Nowadays in Kazakhstan there has been a steady tendency towards the reduction in the amount of children-orphans and children deprived of parental care. It results from the general growth of people’s welfare, increase of allowances for guardians and trustees, improvement of laws on adoption.
The number of inmates of orphanages and baby houses is constantly decreasing. It is pleasant to observe the statistical figures showing that practically all children’s social institutions are not overcrowded as formerly but, on the contrary, are near-empty. In many regions, the issue of orphanages merger and reorganization is raised.
The same statistics is true for the capital city. The latest data provided by the Astana Administration of Education show that 163 children live in Kazakhstan state establishment Children’s Home with the capacity of 250 people. SOS Children’s Village Astana is meant for 91 children but only 67 children live in it.
So, the construction of Children’s Village of the family type for 100-140 children in Astana planned by Saby Foundation became inexpedient. In this connection, the administration of the Foundation took the decision to terminate the Memorandum with Astana Akimat and stop all works.
Certainly, it is impossible to return all the funds expended for preparation and legalization of documentation on the land plot, geological survey and topography, design of project, which is completely ready for the expertise, and other works. But taking into account the reason for project termination, and namely, that the children, for whom the construction has been planned, will live in real families with loving parents, we are not disappointed but, on the contrary, are glad with this fact.
As for the funds provided by the sponsors for the construction of the Children’s Village, they will be used for the implementation of another project – construction of the Social hostel for the orphanage leavers with health disorders in the city of Aktobe.

Construction of the Children Village. Steps

By | Children's villages of family type in Astana

Construction of the Children Village. Steps The works under the project of “Children Village of Family Type in Astana city” are continued.

The borders of the land parcel for construction, presented by the city, have been defined and marked along the perimeter.

All necessary technical specifications from corresponding service providers have been received.

The sketch of the object has been prepared, which was approved of the city-planning council of Astana. Simple and convenient solutions for comfortable living of orphan children and children without parental care are used in the project.

Construction of the Children Village. Steps.

By | Children's villages of family type in Astana

We have already informed that a land parcel was allotted for Saby Foundation in Astana city for the construction of children village of family type for orphan children and children left without parental care. Now our colleague prepares necessary documents for the land parcel.

Besides, it is necessary to solve many tasks on the stage of planning and preparation to the construction. One of the tasks is the engineering, geodesic and geological investigations on the land parcel. At the present time this work has been done. All information received in the result of topographical survey and soil exploration is extremely necessary for the development of design and estimate documentation which will become the next step in the project.

Follow our news.

What the Children’s Home Lives By

By | Orphanage in Kyzylorda

What the Children’s Home Lives By Time flies imperceptibly. This is the second year the inmates of Kyzyl-Orda Children’s Home have lived in a new place, built for them by Saby Foundation. This house has become home for orphans by giving them comfortable atmosphere and warmth in the true sense of the word and razing from the children’s memory dank and grey rooms of the old building.

We have been watching with pleasure how the children’s life was arranged and now is taking place within the walls of the new building. In addition we were particularly concerned about the issue of creating for children an appropriate recreation area in the open air. Initially, in the developmental stage of the construction project, we have devoted much attention to the issue of planting area, since all children’s institutions are to be separated as possible from adjacent territories and streets through the creation of shelterbelts. There was one serious nuance – the local severe climate and salty soils don’t make good germination capacity.

However appropriately selected species of plants, proper planting and care did their job – children run around on the lush grass, enjoy life-giving water of a fountain and rejoice at bright flowers’ colors. And for supper a cook prepares for them tasty dishes from fresh vegetables harvested in own beds.

May this oasis around the Children’s Home expand and probably in time it will become a green pearl of the city at which people will come to have a look.

Русский

Қазақ тілі

English